Ten emergency power plants and Norwegian turbine did not reach Moldova

The Ministry of Energy says the purchase of 10 modular power plants and a 125 MW turbine failed due to missing equipment and logistics problems.

0 comments

Written later, from the reports of that day.

Ten emergency power plants and Norwegian turbine did not reach Moldova
Photo: TV8

What it means for you

The emergency plants that were to be installed three to five months after delivery will not come to Moldova. The Ministry of Energy has not yet announced other solutions to strengthen the power system. The reports give no new date or sum for this project.

What happened

The Ministry of Energy confirmed that the purchase of 10 modular power plants, 100 MW in total, did not succeed. The 125 MW gas turbine from Norway was not moved to Moldova either. The ministry says calls through the EU Civil Protection Mechanism found no available capacity.

In short

  • Moldova asked to activate the EU Civil Protection Mechanism on 17 January 2025.
  • The European Commission issued a repeated call on 6 June 2025, with no result.
  • The turbine generator stator alone weighs about 125 tonnes, according to the ministry.
  • A 2025 pre-feasibility study found major transport and infrastructure problems.

Original sources

  1. Planuri rămase doar pe hârtie: De ce nu au mai ajuns în Moldova centralele electrice de urgență și turbina din Norvegia · in RomanianRead it on TV8
  2. De ce nu au mai ajuns în Moldova centralele de urgență și turbina din Norvegia · in RomanianRead it on Stiri.md

Summary written automatically by pizdet.md from the articles above. Read the originals for the details. Found a mistake? Tell us

Press it if you feel the same

Read also

Comments 0

  1. Loading comments…

Menu

Sections

About the project

Language

Theme