Vulcanesti-Chisinau power line delayed again, minister says
The Energy Minister says commercial operation of the 400 kV line could start at the end of October or early November.
Written later, from the reports of that day.
What it means for you
The company gave the minister its latest deadline: the end of October or early November for commercial operation to start. No final date has been announced yet. Until then the line does not enter commercial operation.
What happened
Energy Minister Dorin Junghietu said the commissioning of the 400 kV Vulcanesti-Chisinau power line is delayed again. The line was due to start operating in December last year. The company's latest deadlines, according to the minister, are the end of October or early November.
In short
- The commissioning has now been postponed for the sixth time since December last year.
- The line was ready in mid-year, and voltage tests were carried out on it.
- The delay started with a transformer that was sent to Spain for repair in early summer.
- The transformer returned on 23 or 24 September and was installed and connected.
Original sources
- Darea în exploatare a liniei Vulcănești-Chișinău este din nou amânată · in RomanianRead it on Point.md
- Ввод в эксплуатацию линии Вулканешты-Кишинев опять откладывается · in RussianRead it on Point.md
Summary written automatically by pizdet.md from the articles above. Read the originals for the details. Found a mistake? Tell us
Press it if you feel the same